41,000 Sq Ft Office Heat Pump Retrofit

TI delivered a turnkey high-temperature heat pump solution to replace legacy gas systems

clslogo

Project Snapshot

Vista icons (1)
Location:
51 Clarendon Rd, Watford
asset
Asset:
41,000 sq ft office building
Vista icons (3)
System Capacity:
300kW HT heat pumps (80°C flow)
time
Duration:
6-week installation

Challenge & Objectives

TI was appointed to deliver a rapid and future-proof gas boiler replacement. The challenge was to retrofit a high-capacity, low-carbon system without costly grid upgrades or disruption to existing tenants.

Our Solution

Key Outcomes

Installation completed in just 6 weeks

Improved EPC rating and lower operating costs for tenants

Decarbonised heating without major infrastructure upgrades