Office Building
An intrusive inspection that found every electrical connection sound — and traced the real problem to a building leak, not a wiring fault.
15
Outgoing ways inspected
6
MCCBs on the ingress side
£40–60K
Recommended budget
3–6
Months, recommended timing
What We Found
Every connection tight — six devices in question
Every termination in the panel was checked and confirmed tight — no loose connections anywhere. But six of the eleven MCCBs sit on a side of the panel exposed to long-standing water ingress, and being sealed, non-serviceable devices, their internal condition after years of intermittent damp can’t be verified.
The Recommendation
Two remedial options
Two options were costed. Only one disturbs equipment that TI’s inspection confirmed is already in good condition.
What Actually Changes
How the recommended option works
The panel is split along the line shown below — the left-hand main switch and incoming cable chamber stay in service; everything to the right, including the water-damaged end, is replaced with a new wall-mounted panel.
Our Process
Electrical Lifecycle Testing
Every TI survey follows the same four-stage method — evidence before decisions, decisions before capital.
What TI delivered
Diagnosis
Root Cause
RECOMMENDATION
The Result
15 / 15
Ways checked, zero loose connections
1
Root cause found — a leak, not a fault
£15–90K
Saved with the right-sized fix
Stop replacing electrical infrastructure on a guess.